        Repurposing the unfinished MOX facility as SRPPF allows NNSA to make             SRPPF IS SUBJECT to
        use of an existing Hazard Category-2 structure, which was designed               the National Environmental
        to rigorous nuclear safety and security standards, including interior            Policy Act, which requires
        walls of reinforced concrete to provide personnel shielding. It also             that potential environmental
        provides numerous supporting facilities, including office, assembly, and         impacts be considered before
        fabrication space; construction facilities; and existing SRS services and        a government agency decides
        infrastructure, such as security, electrical, fire protection, and emergency     to undertake an action. That
        response. Repurposing the facility requires decommissioning and                  evaluation was completed for
        removal of MOX equipment and commodities, internal modifications and             SRPPF in November 2020, with
        installation of plutonium processing and infrastructure support equipment   the publication of the Record of Decision announcing the
        directly associated with the pit production mission.          NNSA’s decision to implement the Proposed Action to
        The CD-1 cost estimate for SRPPF is $6.9 - $11.1 billion, with an overall   repurpose the MOX Fuel Fabrication Facility to produce war
        project completion range of 2032-2035. The CD-1 cost estimate and   reserve pits.
        project completion date ranges are preliminary estimates that will be   The evaluation process included a public comment period
        refined as the project conceptual design is matured to the 90% design   in 2019 to guide the drafting of a detailed Environmental
        level required to achieve CD-2 (approval of the performance baseline).   Impact Statement (EIS), followed by another public
        Consistent with industry best practices and DOE policy, NNSA will set the   comment period after the Draft EIS was published in April
        performance cost and schedule baseline at CD-2, which is expected in   2020. Following consideration of the comments received,
        FY 2024.                                                      and the resulting changes to the Draft EIS, the Final EIS was

        NNSA and SRNS will continue to review this project to improve the fidelity   published in September 2020, and formed the basis for the
        of the current price estimate and schedule.                   Record of Decision.